Line 19 (Beijing Subway)

Line 19 of the Beijing Subway (Chinese: 北京地铁19号线; pinyin: Běijīng Dìtiě shíjiǔ hàoxiàn) is a rapid transit line in Beijing. It is 22.4 km (13.9 mi) in length and has 10 stations (6 stations in operation). It is fully underground.[2]

Line 19
A CCD5034 train leaving Mudanyuan station
Overview
Other name(s)M19 / R3 (planned name)
StatusIn operation
TerminiMudanyuan
Xingong
Stations10 (6 in operation)
Service
TypeRapid transit
SystemBeijing Subway
Operator(s)Beijing Metro Operation Administration (BJMOA) Corp., Ltd.[1]
Depot(s)Xingong
Rolling stock8-car Type A (CCD5034 and SFM80)
History
Opened31 December 2021 (2021-12-31)
Technical
Line length22.4 km (13.9 mi)[1]
CharacterFully underground[2]
Track gauge1,435 mm (4 ft 8+12 in)
Operating speed100 km/h (62 mph) (Phase 1)[3]
Route map

planned extensions
Mudanyuan
outer – inner
Xiaoyue river
Beitaipingzhuang
SijiqingGuanzhuangluxikou
North Hucheng river
Jishuitan
outer – inner
Line 4 Anheqiaobei
Ping'anli
Line 3 (Phase 2, long-term planning)
Line 3 Caogezhuang North
Line 4 Tiangongyuan
Line 3 Tiancun
Taipingqiao
Line 1 crossing
Line 2 crossing
Niujie
Line 7 crossing
South Hucheng river
Jingfengmen
Liangshui river
Daxing Airport Express Lize Shangwuqu
Ma'cao river
Caoqiao
inner – outer
Xinfadi
Xingong depot
Xingong
Daxing line (through operation to Line 4)
planned extensions

Description

Phase 1 of Line 19 begins at Mudanyuan station in Haidian District and ends at Xingong station in Fengtai District.[4] The line is 22.4 km (13.9 mi) in length with 10 stations of which 4 are still under construction.[5] The line was envisioned as a major relief line for the overcrowded Line 4 and more direct link to the Beijing Financial Street commercial area.

The line uses 8-car type A rolling stock.[3][6]

The trains have a maximum speed of 120 km/h. However the speed limit of the first phase, which runs under the dense city center is 100 km/h.[7][8] Phase II extensions north and south run through suburban areas and will be built to more generous alignments allowing for 120km/h operations.

Opening timeline

SegmentCommencementLengthStation(s)Name
Mudanyuan — Xingong 31 December 2021[9][10] 22.4 km (13.9 mi) 10 Phase 1

Stations (Phase I)

Legend

  - Stations not in operation, opening in 2022 or later

Station Name Connections Nearby Bus Stops Distance
km[11]
Location
English Chinese
Mudanyuan 牡丹园  10  16 21 22 47 123 135 304 331 345快 425 508 510 579 601 606 618 620 645 653 658 夜4 夜9 0.00 0.00 Haidian
Beitaipingzhuang 北太平庄  12  0.92 0.92 Haidian/Xicheng
Jishuitan 积水潭  2  5 22 27 44 47 55 80 88 135 143 200 331 344 345 345快 347 380 409 508 604 618 620 625 670 872 877 883 885 886 889 919 919快 观光3 夜2 夜4 夜20 夜36 夜38 专31 专51 专168 2.45 3.37 Xicheng
Ping'anli 平安里  4   6  1.59 4.96
Taipingqiao 太平桥[12] 2.71 7.67
Niujie 牛街 5 6 10 38 48 50 57 88 109 381 夜7 夜23 专13 1.24 9.81
Jingfengmen 景风门  14  2.96 12.77 Fengtai
Caoqiao 草桥  10   Daxing Airport  381 410 423 434 456 483 497 529 676 679 夜22 专179 专209 2.68 15.45
Xinfadi 新发地 353 354 377 381 410 423 454 483 497 529 646 676 679 夜22 专190 2.65 18.10
Xingong 新宫  Daxing  343 353 354 369 474 556 827 829 946 954 专59 专67 专190 2.74 20.84

    History

    It was reported in February 2012 as one of six new lines under planning by the city's public transit planning authorities. As of 2015, the line was renamed to Line 19[13] with the first phase starting construction in 2016.[4] The line opened in 31 December 2021, but 4 stations is still unopened.[14][15]

    Future development

    Phase 2 of Line 19, which is under planning, consists of a northern extension to Changping District. Additionally, there will be a branch line of the northern extension, which will serve the rebuilt Qinghe railway station, a station on the Beijing–Zhangjiakou intercity railway.[16] On 11 January 2022, the second phase of Line 19 was listed as one of the 10 construction projects in the "Beijing Rail Transit Phase III Construction Plan (2022-2027)"[17]

    References

    1. "定了!地铁19号线,北京轨道运营公司运营". 2019-12-12.
    2. "北京地铁19号线一期首次披露10座车站及运行线路-新闻频道-手机搜狐". Sohu.
    3. 北京地铁19号线无缝对接新机场线 10站中8站能换乘-千龙网·中国首都网. beijing.qianlong.com. Retrieved 2017-03-24.
    4. "北京地铁19号线一期预计2020年完工 系首条南北地铁快线-新华网". www.xinhuanet.com. Retrieved 2018-07-21.
    5. "北京地铁19号线将设10座车站8座能换乘 年内开建 北京日报 2015-8-27" (in Simplified Chinese).
    6. 北京地铁19号线一期全部车站开建 计划于2020年通车-千龙网·中国首都网. beijing.qianlong.com. Retrieved 2018-05-29.
    7. "北京多条在建地铁完成铺轨". 2021-08-01. 作为穿越中心城区的轨道快线,19号线最高时速达到100公里
    8. "北京地铁19号线一期预计2020年完工 系首条南北地铁快线". 2018-07-18. Archived from the original on 2019-05-24. Retrieved 2019-05-24. 一期工程受土建实施限制限速100km/h
    9. "北京今年年底预计开通7条(段)地铁 总计约54公里". 2021-02-26.
    10. "Seven Subway Line Sections in Beijing to Open by End of 2021". The People's Government of Beijing Municipality. 2021-12-13. Archived from the original on 2022-01-13. Retrieved 2022-01-13.
    11. "19号线路网车站站间距信息". Retrieved 2022-02-18.
    12. "地名公告>太平桥站". 2021-11-09. Retrieved 2021-11-09.
    13. "北京地铁17号线二次环评公示 拟撤永安里北站_央广网".
    14. "19号线草桥以南后年先行开通". 2019-07-03.
    15. "编制轨道交通新一轮建设规划". 2019-02-27.
    16. 北京地铁19号线一期计划2020年底开通. www.bj.xinhuanet.com. Retrieved 2017-03-24.
    17. "北京市轨道交通第三期建设规划环境影响评价第一次公示_信息公开_北京市基础设施投资有限公司". www.bii.com.cn. Retrieved 2022-01-28.
    This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.