DND–KMP Expressway
DND–Faridabad–KMP Expressway is an under-construction 59 km long, 6-lane wide access-controlled expressway in Delhi NCR, India.[1] It will connect the junction of DND Flyway and Ring Road at Maharani Bagh in Delhi with KMP Expressway at Khalilpur village, Nuh district in Haryana. Now, it is a part of Delhi–Mumbai Expressway project.
DND–KMP Expressway | |
---|---|
डीएनडी–केएमपी एक्सप्रेसवे | |
Route information | |
Maintained by National Highways Authority of India (NHAI) | |
Length | 59 km (37 mi) |
Existed | May 2023 (expected)–present |
Major junctions | |
North end | DND Flyway, Maharani Bagh, Delhi |
South end | KMP Expressway, Khalilpur, Nuh district, Haryana |
Location | |
Country | India |
States | Delhi and Haryana |
Major cities | New Delhi, Noida, Faridabad, Ballabgarh, Palwal and Sohna |
Highway system | |
In Haryana, it will pass entirely through existing Faridabad bypass road. The HSVP has transferred the Faridabad bypass to NHAI for the construction of Delhi–Mumbai Expressway project.
Route
NCT of Delhi (09 km)
- Begins in Delhi from the junction of DND Flyway and Ring Road at Maharani Bagh
- Pass through Khizrabad, Batla House and Okhla Vihar on Yamuna river's west bank
- Starts moving exactly along the Agra Canal from Okhla Vihar metro station to Mithapur
- 2nd entry ramp near Kalindi Kunj metro station (towards Mithapur) for traffic from Noida
- Exits Delhi at junction of Jaitpur–Pushta road and Kalindi Kunj–Mithapur road.
Haryana (50 km)
- On Kalindi Kunj–Mithapur road, it will cross the Agra Canal at Sehatpur Bridge (Faridabad)
- Move on Faridabad bypass road from Sector-37, Faridabad to Kail Gaon near Ballabhgarh[2]
- Interchange with Delhi–Agra (NH-2) near DPS Ballabhgarh school at Kail Gaon village
- Crosses Palwal–Sohna (NH-919) at Hajipur village (Gurgaon district)
- Trumpet interchange with KMP Expressway at Khalilpur village (Nuh district).
Construction
The construction work of the 'DND–Faridabad–KMP' section was awarded by the National Highways Authority of India (NHAI) to Dineshchandra R. Agrawal Infracon Private Limited (DRA Infracon) in August 2020.[3] This project will reduce congestion on Ashram to Ballabhgarh route (via Badarpur). In Haryana it will have multiple Flyovers and a 3-lane service road on either side of Faridabad bypass road.
7 km out of 9 km route in Delhi state will be elevated with two-level crossings at 4 locations of the Delhi Metro rail line (near Okhla Vihar and Kalindi Kunj metro station), making it the 1st expressway in India to cross above elevated metro rail line.
The NHAI has divided the construction work of 59 km long DND–Faridabad–KMP section of Delhi–Mumbai Expressway project into 3 packages and its construction cost is around ₹5,332 crores (including land acquisition cost).[4][5]
Sr No | Package | Length in km | Value in crores | State |
---|---|---|---|---|
1. | Junction of DND Flyway & Ring Road in Delhi to Jaitpur–Pushta road in Delhi | 09 | ₹1,881 | Delhi |
2. | Jaitpur–Pushta road in Delhi to Sector-62/65 dividing road in Faridabad | 24 | ₹1,832 | Haryana |
3. | Sector-62/65 dividing road in Faridabad to KMP Expressway at Khalilpur in Nuh district | 26 | ₹1,619 | Haryana |
Note: Package-2 starts at junction of Jaitpur–Pushta road and Kalindi Kunj–Mithapur road in Delhi (near NTPC Eco Park, Badarpur).
Delhi–Mumbai Expressway
The construction work of Delhi–Mumbai Expressway is divided by NHAI into 4 sections with a total of 52 tenders/ construction packages as given below. The entire 1,350 Km long expressway is expected to be completed by March 2023.
Section | Length in km | No. of packages | State-wise packages |
---|---|---|---|
DND–Faridabad–KMP | 59 | 03 | 1 in Delhi and 2 in Haryana |
Sohna–KMP–Vadodara | 844 | 31 | 3 in Haryana, 13 in Rajasthan, 9 in Madhya Pradesh and 6 in Gujarat |
Vadodara–Virar | 354 | 13 | 10 in Gujarat and 3 in Maharashtra |
Virar–JNPT | 92 | 05 | 5 in Maharashtra |
Link with Jewar Airport
The NHAI has announced in August 2021, that an additional 30 km long spur will also be constructed from Noida International Airport in Jewar to Ballabgarh on this expressway.[6]
Link with KGP Expressway
A 12 km long, 4-lane wide highway is also proposed by NHAI in Faridabad district. It will connect Chandawali village on DND–KMP Expressway with Maujpur village on Eastern Peripheral Expressway or EPE (also known as KGP Expressway).[7]
Status updates
- Mar 2019: Foundation stone laid by Union Minister Nitin Gadkari on 1 March 2019 in Mithapur, Delhi.[8]
- Dec 2019: NHAI invited bids for construction in 3 packages under Bharatmala Pariyojana.[9]
- July 2020: Work awarded by NHAI to DRA Infracon Private Limited (Package-1 & Package-2).[5]
- Aug 2020: Work awarded by NHAI to DRA Infracon Private Limited (Package-3).
- Oct 2020: Soil testing work started in Faridabad district of Haryana[10]
- Feb 2021: Construction work is expected to start this year: NHAI.[11]
- May 2021: Construction work started in Package-3 on 14 May.
- Aug 2021: Construction work started in Package-2 (Faridabad bypass) on 10 August.
- Oct 2021: HSVP started demolishing illegal encroachments falling on the RoW in Faridabad.[12]
- Jan 2022: Construction work started in Package-1 (Delhi) on 11 January.
- Mar 2022: Segment Launcher started erection of concrete structures in Maharani Bagh on 21 March. 7 km out of 9 km long (Package-1) is elevated.[13]
References
- "59-km six-lane road to connect DND, Ring Road with Delhi-Mumbai expressway - delhi news". Hindustan Times. Retrieved 4 August 2020.
- "दिल्ली-मुंबई एक्सप्रेस-वे पर हरियाणा के फरीदाबाद से आ रही खुशखबरी, जानें फायदा". Dainik Jagran. 8 April 2022.
- "Work awarded for new Delhi-Mumbai e-way link". Times of India.
- "Delhi NCR: Six-lane highway to connect ring road-DND junction with Delhi-Mumbai Expressway". Times Now. Retrieved 4 August 2020.
- "Contract award status of Delhi–Mumbai Expressway as of May 2021" (PDF). NHAI. 28 May 2021.
- "Jewar International Airport will be linked to Delhi-Mumbai Expressway". News18. 16 September 2021.
- "Link road between Delhi-Mumbai Expressway and KGP Expressway declared as national highway". Dainik Jagran.
- "Nitin Gadkari to lay foundation stone for Rs 3,580 crore project to decongest Delhi". Economic Times.
- "NHAI invites bids for highways under Bharatmala Pariyojana". Construction Week Online. 22 December 2019.
- "Soil testing for Delhi-Mumbai Expressway link begins in Faridabad". Times of India.
- "NHAI to start work on crucial decongestion projects in Delhi this year". Hindustan Times. 10 February 2021.
- "NHAI to raze 500 structures for Delhi-Mumbai Expressway". The Tribune. 9 October 2021.
- "दिल्ली-मुम्बई एक्सप्रेसवे के पहले चरण का निर्माण शुरू, नोएडा से बनकर जा रहा प्री-कास्ट मैटेरियल". TriCity Today. 22 March 2022.